ESO continues renovation of Bulgaria’s electricity transmission network

The completely renovated and reconstructed 110 kiloVolts (kV) substation Targovishte 2 was put into operation by Bulgaria’s Transmission System Operator ESO, in line with its strategy of modernising and upgrading the country’s electricity system.

The substation is an important part of the electricity transmission network of Bulgaria, ensuring the transmission of electricity from the Northern to the Southern part of the country. It is also essential for the integration of electricity produced by renewable energy sources.

The reconstruction will contribute to increasing the security of the electricity supply in the region and increasing the possibilities of connecting new generating capacities to the medium voltage network.

The project for the Digital transformation and development of ESO’s information systems is part of the measures included in the country’s National Energy and Climate Plan. So far, ESO has invested over 130 million levs (66.4 million euros) for the construction of remote control systems and 150 substations have already been automated. By the end of 2024, all 265 ESO substations are planned to be remotely controlled from a base station.